EverWind Fuels announced a 420 MW AI data centre at Point Tupper, with Anthropic leasing the first 95 MW phase for at least 20 years (online by end of 2027; 325 MW more in 2028). EverWind plans four onshore wind farms to supply it and a Membertou-led Mi'kmaw consortium is negotiating a 9% stake. For Baddeck this is the demand case made real: the province now needs new generation near that load, and independent wind already in consultation is the quickest to deliver. We will set out what it means for our offtake plan at the November open houses. CBC report.
Public comment period runs to November 30. The website has been rebuilt around the 2026 federal decisions. Land option discussions are under way with landowners in the study area.
$10 billion in federal financing for Churchill Falls, Gull Island (2,700 MW) and 660 km of transmission, expressly to enable variable renewables in neighbouring provinces. This is the single most important development for the project since incorporation.
A $20 billion clean energy target at the Canada Infrastructure Bank, a clean electricity tax credit, and an Indigenous Loan Guarantee Program doubled to $10 billion. The capital stack for a Mi'kmaw-co-owned project now exists.
Canada and Nova Scotia agree to a single environmental review for major projects. We are planning the EA on that basis, with commercial operation as early as 2028.
Registered under the Companies Act (Nova Scotia). Registered office at 45 Weatherbee Road, Mira Road.
First conversations with landowners and Mi'kmaw communities. Wind resource desk study begun.
Join the newsletter and you will receive each update the day it is posted, and nothing else.